Skip to main content

B.C. minister is angry Kinder Morgan got help after its 'reluctance' to follow rules

British Columbia Environment Minister George Heyman speaks on a panel at the UN climate change summit in Bonn, Germany on Nov. 14, 2017. File photo by Mike De Souza

Support strong Canadian climate journalism for 2025

Help us raise $150,000 by December 31. Can we count on your support?
Goal: $150k
$32k

Canada's pipeline regulator, the National Energy Board (NEB), is giving energy giant Kinder Morgan some new help to speed up its Trans Mountain expansion project — this despite recognizing that the Texas-based company was showing some "reluctance" to follow the rules.

The company has been urging the regulator to circumvent some of the constitutional powers of municipalities and the province of British Columbia after complaining that delays in local permits could jeopardize the completion of the multibillion dollar west coast oil pipeline.

The NEB, which has powers of a federal court, agreed to some of the Kinder Morgan's requests, including the introduction of a new process to fast-track the review of company complaints about delayed permit approvals and resolve them within three to five weeks. In December, the regulator also ruled that it would allow the company to bypass the bylaws of Burnaby in Metro Vancouver. But it didn't say why until it released a 26-page explanation last week that blamed the city for dragging its feet on approvals.

The moves have provoked outrage from both the British Columbia government and Burnaby, which say the regulator is stripping their powers to protect public safety, the environment and the economy.

A three-member panel of the NEB, David Hamilton, Alison Scott, and Philip Davies, wrote that the company finally filed some applications for permits in Burnaby in June 2017, more than six months after Prime Minister Justin Trudeau announced that the federal government was approving the pipeline expansion project in November 2016.

After June 2017, the regulator concluded that Burnaby's response was confusing and inefficient.

"After that point, Burnaby did, at times, indicate that (preliminary approval) application completeness was still a concern," said the ruling. "However, at other times, Burnaby cites the Project’s complexity or the fact that Burnaby has many other (preliminary approval) applications under review as being reasons for the delay. Even if it were true that significant material was still lacking after June 2017, there was no clear, consistent, or meaningful effort on Burnaby’s part to make it known to Trans Mountain what was specifically required to complete its applications."

No 'concerted effort' to make progress

Both the city and the province of British Columbia dispute the NEB's assessment, arguing that Kinder Morgan is to blame for failing to follow the rules for seeking permits.

After reading the ruling, Gregory McDade, a lawyer for the city of Burnaby, noted that the NEB found no evidence of political or deliberate interference to delay the process.

“Based on that, the NEB has no jurisdiction to do anything else. But instead they determined, based on God knows what evidence — because there certainly wasn’t any evidence of this — that in their opinion, the process was confusing and unreasonable and took too long,” McDade told National Observer in an interview on Friday.

The NEB ruling said that both the city and the company were slow to get the ball rolling after Trudeau gave them the green light.

“…There appears to have been a lack of a concerted effort on the part of both Trans Mountain and Burnaby to meaningfully engage or make any significant progress in late 2016, which carried over to early 2017,” said the NEB.

Burnaby is among the fiercest opponents of the pipeline expansion project since it would be the location of a new expanded oil terminal that would send out large tankers with exports containing bitumen, the tar-like heavy oil derived from Alberta’s oilsands region.

Oil companies say the pipeline is needed to boost growth and jobs by giving them access to new markets in Asia, while opponents, such as Burnaby and several First Nations say the project is too risky and will push Canada’s climate change goals out of reach.

Kinder Morgan says NEB changes are 'good news'

Kinder Morgan Canada president Ian Anderson praised the latest NEB decision.

“Provision of a process that is open, fair and provides certainty for all parties is good news and is an important component of the assurances we need for the successful execution of the Trans Mountain Expansion project,” Anderson said in a statement released on Thursday.

The company had previously warned this week that its project was now a year behind schedule, due partly to delays in getting permits. It now hopes that the pipeline will be in service by December 2020, after the next federal election in Canada.Trans Mountain didn't respond to a question from National Observer about why it failed to make a "concerted effort" to get its municipal permits from Burnaby before June 2017.

The B.C. government said it was considering an appeal.

“I’m angry on behalf of British Columbians,” said B.C. Environment Minister George Heyman in a separate interview with National Observer on Friday. “This is another example of the National Energy Board essentially finding a way to overrule British Columbia’s jurisdiction and assist Kinder Morgan in short-circuiting our legitimate permitting processes that we have a right to have.”

Heyman added that the NEB's decisions could harm the province’s capacity to protect its interests, its coasts and its economy.

“Kinder Morgan could advance no evidence whatsoever that we have been unreasonable in our processes or in handling their permits," Heyman said. "If there is a delay, if there are 900 or so outstanding permits, Kinder Morgan should look themselves in the mirror for failing to apply the diligence that they need to do to get their information in, in a timely and complete manner.”

He also noted that the NEB didn’t concede to all of the company’s requests to reduce oversight on permits.

The NEB panel also refused to require Kinder Morgan to pay for the costs incurred by municipalities as the result of disputes, because it says it expects the parties to work together in "good faith."

It also said it did not want to intervene in local processes for permits, saying it would only do so in limited circumstances.

"The Board is not an appropriate forum to work through any and all difficulties or disagreements encountered during permitting processes, and the generic process is not to be used as a negotiating tool," the NEB panel said. "Rather, the Board’s primary role is to ensure Trans Mountain complies with Project conditions."

McDade, Burnaby's lawyer, said he didn’t yet know if the city would appeal the NEB decision, but noted that Kinder Morgan’s legal challenge actually wound up stalling the municipal permitting process, which caused more delays.

Comments