Skip to main content

Indigenous groups press judge to halt US-Canada pipeline work

#354 of 1611 articles from the Special Report: Coronavirus in Canada
Pipes intended for construction of the Keystone XL pipeline are shown in Gascoyne, N.D. on Wednesday, April 22, 2015. File photo by The Canadian Press/Alex Panetta

Indigenous and environmental groups in the U.S. are pressuring a federal judge to shut down work on the disputed Keystone XL pipeline from Canada to Nebraska less than two weeks after it started, because of fears over workers spreading the coronavirus and worries about a future spill.

Pipeline sponsor TC Energy is rushing ahead amid the pandemic as it tries to complete significant work on the pipeline to make it harder to stop, attorneys for several tribes and groups said in court documents ahead of a Thursday teleconference hearing to decide if the construction should be halted.

They warned that plans to build construction camps housing up to 1,000 workers each “pose serious, immediate and irreparable health risks to the tribes during the COVID-19 pandemic."

“The healthcare systems in tribal and rural communities are already strained to provide basic healthcare services, much less the critical emergency services necessary to responded to an outbreak of COVID-19," said lawyers for the Rosebud Sioux Tribe of South Dakota and the Assiniboine and Gros Ventre tribes of the Fort Belknap reservation in Montana.

President Donald Trump is a champion of the $8 billion project and gave it a presidential authorization in a bid to circumvent a 2018 court ruling that had blocked it.

Tribes press judge to halt US-Canada pipeline as work starts

The same judge who made that ruling will preside over the hearing to decide if construction should be stopped while the court considers if Trump's authorization was legal.

Late Wednesday, Morris handed another setback to TC Energy with a ruling that invalidated a key U.S. Army Corps of Engineers clean water permit. The so-called nationwide permit applied to a broad range of projects including Keystone XL, and is needed to so the pipeline can cross rivers, streams and other waterways.

Keystone XL would have hundreds of those crossings along its 1,200-mile (1,930 kilometre) route from Hardisty, Alberta to Steele City, Nebraska. It would carry up to 830,000 barrels (35 million gallons) of crude daily and opponents say a spill is inevitable.

Workers on Monday installed the first section of pipe across the U.S.-Canada border in northern Montana, according to court documents filed by the Calgary-based company.

The border crossing doesn't require the Army Corps permit that was thrown out because there are no nearby waterways. But it's an obstacle to much further work, and a company spokesman warned the judge's ruling has broad implications for projects across the U.S.

“The ruling directly impacts various utilities constructing and maintaining infrastructure projects, including natural gas, liquids, television cable, electrical transmission, telephone, internet, among others," pipeline spokesman Terry Cunha said. “This decision hampers their ability to build or maintain infrastructure projects in wetlands and water bodies across the U.S."

The Army Corps referred questions to U.S. Justice Department spokesman Wyn Hornbuckle, who said government attorneys were evaluating options but provided no further details.

TC Energy plans to drill tunnels for the pipeline deep beneath major river crossings and says it will be operated safely. The company has a history of spills from other oil pipelines it operates, including a 2017 accident near Amherst, South Dakota that spilled almost 10,000 barrels (407,000 gallons) of oil.

TC Energy’s surprise March 31 announcement that it planned to start construction on Keystone XL amid a global economic crisis caused by the coronavirus pandemic came after the provincial government in Alberta invested $1.1 billion to jump-start the work.

Tribal leaders and some residents of rural communities along the pipeline’s route worry thousands of workers needed for the project could spread the virus in small communities that are unprepared.

TC Energy wants to “use this construction as justification for allowing the project to proceed whether or not it is legal,” the tribes' attorney said.

As many as 11 construction camps, some housing up to 1,000 people, were initially planned for the project. TC Energy says those are under review amid the pandemic and won’t be needed until later in the summer.

For most people, the coronavirus causes mild or moderate symptoms, such as fever and cough, that clear up in two to three weeks. For some, especially older adults and people with existing health problems, it can cause more severe illness, including pneumonia and death.

The rural counties along the pipeline's route so far have seen far fewer infections than other parts of the U.S. But they lack adequate health care services to deal with a large outbreak.

Construction on two worker camps could start as soon as this month in Montana and South Dakota, according to court documents filed by the company.

The construction under way in Montana involves about 100 workers. It's exempted from Democratic Gov. Steve Bullock’s March 26 “stay at home” directive, which is aimed at preventing the spread of the virus by discouraging many daily activities, according to state officials.

The directive did not address worker camps. Bullock spokeswoman Marissa Perry said the governor wants all coronavirus concerns addressed before TC Energy finalizes its plans in areas requiring camps.

Comments